Big Rivers Electric Corporation
Watershed Geo recently worked with Big Rivers Electric Corporation on the final closure of Phase 1 of their Coal Combustion Residuals (CCR) landfill located in Centertown, Kentucky. When deciding the best closure system for this project, Big Rivers chose ClosureTurf® for two main reasons: the system negated the need for a traditional clay cover, and it […]
Rush Island Energy Center Ash Pond Closure
Ameren Corporation, a Missouri and Illinois power company, chose to use ClosureTurf® for their 111-acre Rush Island Ash Pond Closure located in Festus, MO. Rush Island is the third-largest energy center operated by Ameren Missouri. ClosureTurf helped to eliminate many of the issues presented in a traditional landfill cover. Using ClosureTurf on this project eliminated […]