Tiverton Landfill

Tiverton, RI

Project Type

Product Type

ClosureTurf® - (100% Green)

Owner

Town of Tiverton

Engineer

Pare Corporation

Installer

New England Liner Systems Inc.

Size

21.9 Acres

Date Completed

2023

Challenge 

As Rhode Island’s last municipally owned landfill, the Tiverton Landfill reached its final closure in 2022 after extending operations two years beyond its anticipated closing date. The Town of Tiverton needed a proven, long-term closure solution for the 21.9-acre site that would minimize installation time, reduce ongoing maintenance costs, and eliminate challenges associated with traditional vegetated covers. 

Solution  

Building on the proven performance of ClosureTurf® at other landfills throughout Rhode Island, the Town of Tiverton selected the engineered closure system for Phases I–IV of its final closure. Unlike traditional vegetated caps, ClosureTurf® eliminates the need for additional cover soil, allowing for faster installation while reducing truck traffic and transportation-related safety risks. 

Result  

ClosureTurf® provided the Town of Tiverton with a durable, low-maintenance closure solution designed for long-term performance. By eliminating the need for mowing and reducing erosion-related maintenance, the system significantly lowers ongoing maintenance requirements and associated costs. The result is a more efficient, cost-effective approach to landfill closure that delivers lasting value to the community. 

Keep Exploring Projects

Southeastern Wood Preserving Site

Canton, MS

DOE Oak Ridge Environmental Management Disposal Facility (EMDF)

Oak Ridge, TN

Colton Landfill

Colton, CA

Kpone Landfill Closure

Tema, Ghana

TVA Project Phoenix – Shawnee Fossil Plant

Paducah, KY

Taylor County Landfill

Mauk, GA

LEARN MORE ABOUT HOW WATERSHED GEO® PRODUCTS CAN HELP YOUR NEXT PROJECT.

Click below to reach one of our representatives for more information, request product samples, schedule a tour of one of our facilities and more.